Clayton Elementary
Clayton construction is estimated to begin in June 2017 and go through August 2018. Clayton students will begin school in their new building in August of 2018.
Construction Updates
July 30, 2018
July 16, 2018
July 9, 2018
July 2, 2018
June 25, 2018
June 18, 2018
June 11, 2018
June 4, 2018
May 29, 2018
May 21, 2018
May 14, 2018
May 7, 2018
April 30, 2018
April 23, 2018
April 16, 2018
April 9, 2018
April 2, 2018
March 26, 2018
March 19, 2018
March 12, 2018
March 6, 2018
February 27, 2018
February 2, 2018
January 11, 2018
January 4, 2018
December 14, 2017
December 7, 2017
November 30, 2017
November 16, 2017
November 9, 2017
November 2, 2017
October 26, 2017
October 19, 2017
October 12, 2017
October 5, 2017
September 28, 2017
September 14, 2017
September 7, 2017
August 30, 2017
August 23, 2017
August 14, 2017
July 31, 2017
July 12, 2017
July 10, 2017
June 29, 2017
Drone Photos - Week of September 18, 2017
View: Clayton Elementary Construction and Student Location Timeline
Floor Plan
Please see the floor plan for the new Clayton Elementary here.
Project Partners
Architect: Wold Architect & Larson Incitti Architects
Civil Engineer: JVA
Commissioning Agent: Engineering Economics
Furniture Design:
Geotech:
General Contractor:
Landscape Architect: Design Concepts
MEP Engineer: ME Group
Project Management: CBRE
Structural Engineer: BKBM Engineers
Survey:
Technology Engineer: RimRock
View: Facility Performance Scorecard and Needs (includes photos)
Clayton Elementary will receive the following additional upgrades and features:
- Dedicated parent and bus drop-off lanes
- New parking lot
- New age-appropriate playgrounds
- Existing Community Garden to remain
- Improved night-time use
- Entry moved to a less busy street
- Secure entry
- Dedicated gymnasium
- Dedicated cafeteria
- Flexible learning commons designed to support 21st Century Learning
- Varied learning spaces
- Break-out spaces for small group learning
- High-quality day-lit classrooms designed to improve student performance