Project Timeline

Englewood Schools has partnered with CBRE for project management of this multi-school construction endeavor.
 
Here is the estimated construction timeline:
  • Clayton Elementary and Charles Hay World School - June 2017 to August 2018
  • Maddox ECE site - August 2017 to November 2018
  • Bishop site and Cherrelyn Elementary - June 2018 to November 2019
  
For a detailed list of tasks related to phase one, see below. 
 
 
Phase One - Clayton Elementary and Charles Hay World School 
TaskStart Date   Completed?
 RFPs for Architecture and Engineering, Survey, Geotech 11/15/16   Yes
 Design Process12/2016 Yes
 Commissioning2/8/17
 No
 Material Testing4/12/17
 No
 Building Permit Process5/24/17   No
 Construction6/15/17 No
 
 